Work in Progress

September 2018: work in progress!

After the first pile celebration on 13 July, a lot of hard work has gone on at Spinder.

The pile driving activities were completed before the construction industry holiday period and this meant that after the construction break a start could be made on the foundations.

The foundations (1.1 km long in total) are being poured in 3 stages.
The first stage was the production area foundations and this has already been successfully completed.

The hollow-core slabs for the ground floor of the office were installed last week and in the coming weeks the sand-lime brick interior walls will be glued.

  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten
  • Spinder work in progress in Drachten